- Status
- Rezoning approved 4-3 (Jul 2, 2024)
- Developer / parties
- Red Ace Capital Management
- Location
- Stevensburg area, Culpeper County
- Size
- Two four-story data centers of 290,000 sq ft each (1.16 million sq ft) plus an electrical substation on 69.19 acres (DCD)
- Investment
- $350 million; completion not before 2028 (DCD)
- Reported benefits
- DCD reported expected business personal property tax revenue of $14 million to $19 million a year (as reported by DCD)
- Concerns / impacts
- Residents raised noise, water and power use and natural-resource impacts at the hearing (DCD)
- Last verified
- 2026-11-02
Milestones
- Jun 4 2024 public hearing, then at the applicant's request the Board delayed its final vote to Jul 2 (PEC)
- Jul 2 2024 Board approved rezoning 69.19 acres from Rural to Light Industrial, 4-3 (DCD, citing the Culpeper Star-Exponent; the approval itself rests on that one article)
Related records
2024-07-02
Board of Supervisors News report
Board approved rezoning of 69.19 acres from Rural to Light Industrial for Red Ace Capital's two-building, 1.16 million sq ft data center campus on Keyser Road, 4-3 (DCD citing the Culpeper Star-Exponent). (Source article dated Jul 8, 2024.)
Source: datacenterdynamics.com ↗Sources
- News report datacenterdynamics.com
- News report pecva.org
Free weekly digest
Email digest: not open yet
The free weekly email digest is not accepting signups yet, and we collect no email addresses on this site. Every locality and project page is free to read now.
Want it same-day? Neighbor, $4/mo.